- Why does a repair that is “in the black on the invoice” not mean profit?
- How do you keep repair accounting in a service center in seven steps?
- How much did the service really earn on this repair?
- What does the mechanic’s piecework pay show?
- How do you check a work order before issuing the invoice?
- What changes for a warranty repair?
- What does this give?
- Scenario limits
- FAQ
- Repair accounting in a service center is kept on a work order: services, spare parts, pay and the mechanic in one document. Expenses accumulate on it, and the certificate of completed work is created from it.
- For a notional trailer repair, spare parts €460 + subcontractor €162.50 + mechanic's work €120 = €742.50 of cost. The customer's invoice is €1,025, the profit is €282.50, or 27.6%.
- Spare parts are written off to the work order from the defect list, the mechanic gets piecework pay with the operation type "Work order", and the subcontractor creates a debt and a cost. The total shows in the "Accumulated cost" report.
The company is fictional. Every action in Bimp is a real product feature. The figures in the example are invented, and the arithmetic can be checked on a calculator.
Repair accounting in a service center starts with one document that collects everything: what was done, which spare parts were fitted, how much the mechanic and the subcontractor were paid. A notional trailer repair was closed with an invoice of €1,025. The cost was €742.50: spare parts €460, subcontractor €162.50, mechanic’s work €120. The profit is €282.50, or 27.6% of the invoice. Before, nobody named this figure at the end of the month.
Why does a repair that is “in the black on the invoice” not mean profit?
“AgroMash Service” (a fictional company) makes trailers for agricultural machinery and has 55 employees. A separate service center repairs customers’ equipment and its own warranty units. Repairs were recorded like a sale: spare parts were written off with different documents, the mechanic’s pay was calculated in a spreadsheet, and the subcontractor was invoiced separately.
A customer brought in a trailer with a worn axle and brakes. The invoice came to €1,025, the customer paid, and everyone considered the repair a success. But what it cost the service itself could not be found out anywhere: spare parts sat in one document, pay in another, and the subcontractor’s invoice arrived the following month.
The invoice is made up like this.
| Invoice component | Amount, € |
|---|---|
| Spare parts | 600 |
| Subcontractor service (restoring the axle seats) | 200 |
| Mechanic’s work (12 h × €18.75) | 225 |
| Total to the customer | 1,025 |
Check: 600 + 200 + 225 = 1,025. The invoice is known. The expenses are unknown, and those are what must be collected on one document.
How do you keep repair accounting in a service center in seven steps?
Each step is described in the help, with a link next to it. Similar logic of collecting expenses on an order is covered in the article Custom Furniture Cost Calculation.
Step 1. The customer’s equipment and the work order. In Service and repair → Work orders create a document: customer, contract, work completion time, warranty period, responsible manager. The customer’s equipment is added on the “Equipment” tab, and equipment groups are kept in a reference list (Work order, Product groups).
Step 2. Services and spare parts. On the “Services” tab add the work, on the “Products” tab the spare parts with a reserve. Payment is set here too: settlement type, account, deferral. For a typical repair that recurs, create a service specification with material norms, and the new order is filled in from it.
Step 3. The defect list. After inspection the mechanic draws up a “Warehouse defect list”: what to replace, how much is needed, which warehouse to take from. The storekeeper sees the issue plan, and the “Issued” column shows the fact (Warehouse defect list). For our trailer these are a hub with bearings, brake pads and seals.
Step 4. Writing spare parts off to the repair. From the defect list create a “Stock transfer (to cost price)” document. The operation type is “To cost price”, and in the expense item column stands an item of the “Cost price” group, for example “Work in progress”. The spare parts go to this work order. If an administrative item is chosen, the amount goes into company expenses and the repair shows zero (Service cost price).
Step 5. The subcontractor. For work done by an outside workshop, a supplier order with the subcontractor’s service is created from the work order, and then a “Goods receipt” of that service. A debt arises, visible in the “Settlements with suppliers” report, and the amount moves into the cost price of the repair.
Step 6. Piecework pay for the mechanic. In the “Piecework pay” document choose the operation type “Work order” (Piecework pay). The mechanic’s accrual goes into the cost price of this repair and does not dissolve in general expenses.
Step 7. The certificate and the report. In the rows of the order and the certificate the description of the work can be expanded in the “Product content, additional details” column (Extended item descriptions), so the customer sees what he pays for. From the work order a certificate of completed work is created with a “Sales of goods and services” document. The Accumulated cost report shows all expenses on the order.
Repairs were recorded like a sale. Spare parts were written off with different documents, the mechanic’s pay sat in a spreadsheet, the subcontractor invoiced separately. The invoice of €1,025 exists, but nobody can say what the repair cost at the end of the month.
The work order holds the services, the spare parts and the responsible mechanic. Spare parts are written off to cost price from the defect list, the mechanic gets piecework pay, the subcontractor creates a debt and a cost. The certificate of completed work is created from the order.
Cost 460 + 162.50 + 120 = €742.50. Invoice €1,025, profit 1,025 - 742.50 = €282.50, or 27.6%.
How much did the service really earn on this repair?
Counting by documents gives this picture.
| Item | Document | Amount, € |
|---|---|---|
| Spare parts | Stock transfer (to cost price) | 460 |
| Subcontractor | Goods receipt (service) | 162.50 |
| Mechanic (12 h × €10) | Piecework pay | 120 |
| Repair cost | 742.50 | |
| Invoice to the customer | Sales of goods and services | 1,025 |
| Profit | 282.50 |
Check: 460 + 162.50 = 622.50, and 622.50 + 120 = 742.50. Then 1,025 - 742.50 = 282.50, and 282.50 / 1,025 = 0.2756, which is 27.6%.
Spare parts came to €460 of the €742.50, or 62% of the cost. The spare parts on the defect list are a hub with bearings at 280, brake pads at 120 and seals with fasteners at 60. Check: 280 + 120 + 60 = €460. On spare parts the service earned 600 - 460 = €140, on the subcontractor 200 - 162.50 = €37.50, on the mechanic’s work 225 - 120 = €105. Together 140 + 37.50 + 105 = €282.50. The figure agrees with the total, which confirms that no expense was lost.
What does the mechanic’s piecework pay show?
The mechanic gets €10 an hour, while an hour costs the customer €18.75. The difference of €8.75 an hour covers the service’s overheads and gives part of the profit. When the accrual goes with the operation type “Work order”, the amount lands on a specific repair. The owner sees that 12 hours of work brought €105 of gross margin and compares it with other work orders.
If two mechanics work on one repair, the accrual is split between them, and the cost of the work order stays the sum of both. How to combine salary and piece-rate pay for one person is described in the article Salary Plus Piece Rate for the Same Employee.
How do you check a work order before issuing the invoice?
Before the certificate, the service manager opens the “Accumulated cost” report for the work order and compares it with the invoice. If the report shows €742.50 and the invoice is €1,025, the 27.6% margin matches the expected one. If the report has fewer spare parts than the storekeeper issued, the write-off document is not posted yet, and the profit is overstated. This check takes a minute and happens before the customer receives the certificate.
The second check concerns the subcontractor. Until his act is received, the €162.50 is not in the cost, and the work order looks more profitable by that sum. So the order is closed after the subcontractor’s service is received.
What changes for a warranty repair?
The service center also repairs its own warranty units, where the invoice to the customer is zero. Such repairs used to disappear from reporting: there is no sale, but spare parts and hours were spent. A work order for a warranty case has the same tabs: defect list, spare parts write-off, piecework pay for the mechanic. Cost accumulates in the same way, and the owner sees what the warranty costs.
Suppose a warranty repair of the same unit went without a subcontractor: spare parts €460 and the mechanic’s work €120. That is €580 of cost (460 + 120) with no revenue at all. If there were ten such work orders in a month, the warranty would cost €5,800. The figure matters to the trailer designers: it shows which unit breaks most expensively. If hub bearings fail most often, the question goes to the bearing supplier and the design of the unit, and the answer sits in the documents.
What does this give?
The service manager sees the profit of every repair next to revenue. If one work order brought 27.6% and the neighboring one 8%, the reason is visible in the cost structure: pricier spare parts, a slow subcontractor or extra hours. For planning, this is the first figure that was missing.
Repair runs in the same system as trailer production. The warehouse, purchasing, payroll and reports are shared, so a separate program for the service is not needed. Bimp is a Ukrainian cloud ERP for manufacturers, and the service center in it is as much a part of the records as the workshop. How this works for makers of agricultural machinery is described on the page Bimp for manufacturers.
Scenario limits
The scenario describes a repair covered by one work order. The expense item from the “Cost price” group is set up in the service cards and write-off documents before the first repair. Subcontractor expenses move into the cost price with a “Cost allocation” document once they have accumulated. Bimp does not suggest the hours norm: it is set by the mechanic or by the service specification. Check the button names in the interface against your version. All amounts in the example are invented.
FAQ
How does a work order differ from an ordinary sale?
A work order holds the services, spare parts, payment, deadline, warranty and the customer's equipment. Repair expenses accumulate on it, and the certificate of completed work is created from it with a "Sales of goods and services" document.
How do you write off spare parts to a specific repair?
Create a "Stock transfer (to cost price)" document from the warehouse defect list. The materials go to the cost price of the work order, and the "Issued" column of the defect list shows the actual issue.
How do you accrue pay to the mechanic for a repair?
With "Piecework pay" and the operation type "Work order". The accrued amount goes into the cost price of exactly this repair.
How do you see the profit of a repair?
The "Accumulated cost" report shows expenses on open work orders, and after the certificate of completed work the "Gross profit" report shows the profit.
In a Bimp ERP demo a specialist draws up a work order for a typical repair of your equipment together with you and shows what it costs.