Custom Furniture Cost Calculation: A €3,000 Kitchen and a 28.3% Margin

A fictional joinery calculates the cost of custom furniture: materials, piecework pay and workshop rent. Steps in Bimp, reports and the margin of one kitchen.

DO
Dmytro ObukhovCo-Founder & CEO
Table of contents
In short
  • The cost of custom furniture is made of materials, the assemblers' piecework pay and a share of workshop rent and electricity. For a fictional kitchen priced at €3,000 it is €2,150, and the margin is 28.3%.
  • The shop owner saw a margin of about 50% because he compared the price with materials alone (€1,500). Piecework pay of €500 and an overhead share of €150 sat in other ledgers.
  • In Bimp these parts are collected with documents: specification, assembly, piecework pay, cost allocation. The result is visible in the "Gross profit" report.

The company is fictional. Every action in Bimp is a real product feature. The figures in the example are invented, and the arithmetic can be checked on a calculator.

Custom furniture cost calculation has three parts: materials per specification, the assemblers’ piecework pay and a share of the shop’s overhead. For the fictional kitchen “Modern” priced at €3,000 that is 1,500 + 500 + 150 = €2,150, and the gross profit is €850, or 28.3% of revenue.

The shop owner in this story thought the margin was almost twice as high. He sells a 2.4-meter kitchen for €3,000, materials for it cost €1,500, and the difference of €1,500 looks like half of the price. Piecework pay for the assemblers and the workshop rent reach him as separate lines in the bank, with no link to the kitchen.

Why does the kitchen margin look like 50% when it is 28.3%?

Greenfield Joinery (a fictional company) has 45 people: three crews of joiners and an assembly area. Board cutting is outsourced to a contractor. The shop makes kitchens and wardrobes for private clients and designers, and also sells hardware through its own online store. The workshop is rented.

In the owner’s head the price of a kitchen is twice the cost of its materials. Everything else passes outside that figure.

ComponentAmount per kitchen “Modern”, €Where it sat before accounting
Materials1,500visible to the owner
Piecework pay for assemblers500a separate payroll account
Workshop rent and electricity150general expenses of the month
Total2,150

The workshop share is calculated like this. In a month the shop makes 12 kitchens, and rent with electricity costs €1,800. Divide: 1,800 / 12 = €150 per kitchen. No kitchen had ever seen this money in its costing.

How does custom furniture cost calculation work in Bimp?

The path from specification to margin takes six steps. Each step is described in the help, with a link next to it.

Step 1. The specification “Kitchen Modern 2.4 m”. It has three stages (cutting at the contractor, edge banding, assembly), materials with a loss percentage and an assembly operation with your rate. The planned cost method is chosen on the “Materials and components” tab: “By remaining cost price” takes the current balance in the warehouse, and “By last purchase price” is convenient for budget planning. A typical specification can be marked as a template, and large sets are loaded from Excel. Details are in the help: Specifications and Import specifications. For our kitchen the plan for materials is €1,450.

Step 2. Customer order and reserve. The manager creates a customer order with the kitchen specification and creates a materials reservation based on it. Boards and hardware are tied to this order and will not go to someone else’s kitchen (Reserve materials).

Step 3. Production order and assembly. When the shop has built the kitchen, the “Assembly” is posted. Materials are written off at actual, and if more boards were used than the norm, the quantity is corrected in the document itself. The finished kitchen goes into the warehouse at its cost. In the example €1,500 was written off against a plan of €1,450, an overrun of €50 (3.4%). See Production order and Assembly.

Step 4. Piecework pay for the assemblers. If the specification has an operation with a rate, piecework pay appears when the assembly is posted, and it can also be created with Create based on from the posted assembly. The €500 lands on the cost of this very kitchen. Next to it you can see which performer received what (Piecework pay, piecework scenarios). The chain from the customer order to the assembly and payments opens on the “Links” tab (The Links tab).

Step 5. Rent and electricity. General workshop expenses are entered with an “Other expenses” document with the “To cost price” switch and without an order (Cost accumulation). At the end of the month a “Cost allocation” document moves the accumulated €1,800 to the 12 kitchens made, by quantity. At the bottom of the document you compare “Allocated” and “Accrued”: if the sums differ, Bimp will not post the document (Cost allocation).

Step 6. Reports. “Accumulated cost” shows how much expense has been accumulated, how much is already allocated and how much is waiting (report). “Gross profit” grouped by orders puts revenue and cost together and gives the kitchen’s profitability (report).

How do you allocate workshop rent to products?

The allocation base is set in the “Cost allocation” document with the Allocate button. “By quantity” divides expenses equally between each unit of output. “By amount” gives pricier products a larger share. For workshop rent, where kitchens are similar in the amount of work, the shop chooses quantity, while for logistics costs amount is the better fit.

The choice of base changes the margin of individual models, although the total stays at €1,800. So the rule is fixed once and not changed every month: then the margins of kitchens in different months can be compared. If an expense item lies outside the “Cost price” type, it will not reach the “Accumulated cost” report, and there will be nothing to allocate. Items are set up before the first document.

Challenge

A kitchen is sold for €3,000. The owner believes the margin is about 50%, because he sees only the materials at €1,500.

Solution with Bimp

A specification, a reserve, an assembly, piecework pay and an allocation of rent put together the cost of the kitchen from all its components.

Result in numbers

Materials 1,500 + piecework pay 500 + rent share 150 = €2,150. Gross profit 3,000 - 2,150 = €850, which is 28.3% of revenue. By materials alone the margin looked like 1,500 / 3,000 = 50.0%, a gap of 21.7 percentage points.

What does the owner see in the reports?

In the “Gross profit” report, the order for the kitchen shows three numbers: revenue €3,000, cost €2,150, gross profit €850. Profitability is 850 / 3,000 = 28.3%. Markup, which is profit to cost, is 850 / 2,150 = 39.5%. Both percentages describe the same money, so in a conversation with the accountant it is worth agreeing which one is discussed.

The breakdown by documents shows which assemblies, piecework payments and allocations made up the cost. The answer to the accountant’s question is in the report itself, with no call to the shop.

Then the owner compares two models. The fictional kitchen “Classic” is priced at €2,350.

Indicator“Modern”“Classic”
Price, €3,0002,350
Materials, €1,5001,000
Piecework pay, €500270
Rent share, €150150
Cost, €2,1501,420
Gross profit, €850930
Profitability28.3%39.6%

The pricier kitchen earns less. For “Modern” to reach 40% profitability, its price must be 2,150 / (1 - 0.4) = €3,583. That is €583, or 19%, more than the current price. The owner decides whether the market will bear such a price, and he has the numbers to decide. He leaves the price of “Classic” alone.

The contractor’s invoice for cutting may arrive after the kitchen has shipped. Then the cost in the sale is updated by reposting, which Bimp does automatically after midnight (Cost recalculation). Reposting the sales document gives an immediate result.

What does this give the company?

The owner gets a mechanism that shows the profit of every product each month. Pricing by eye stops being the only way: a price can be checked against cost before it gets into a contract.

The technologist sees the deviation of plan from actual (€50 per kitchen) and understands where more material goes than the norm. The accountant does not assemble cost in a spreadsheet from three sources, because the specification, piecework pay and cost allocation are already linked by documents. Bimp is a cloud ERP for manufacturers, built in Ukraine, and this whole chain works in one system, with no exports between programs.

The principles of comparing plan and actual are covered in How to Calculate Manufacturing Cost When Excel Keeps Getting It Wrong. The Bimp for manufacturers page shows how to set up such accounting on your own products.

Scenario limits

The scenario shows output by specification with one assembly and an allocation of overhead by quantity. Staged production with production tasks for every product is described in a separate scenario. The “Gross profit” report gives the margin, and the “Cost of Produced Goods” report serves to compare the specification with actual output. Bimp does not guess overhead: rent, electricity and the assembler’s rate are entered first into directories and documents, and only then do they appear in the cost. Some of the help articles behind the steps carry a verification status, so check the button names against your version.

The cost of the kitchen in the fictional shop turned out to be €650 higher than the cost of materials: €500 of piecework pay and €150 of rent share that had gone nowhere before.

FAQ

Can you calculate cost without specifications?

Yes. In the production order you turn on the "Without specification" switch and add the product and materials by hand. There is then no planned cost, so there is nothing to compare plan with actual.

Does workshop rent enter the cost by itself?

No. It is entered with an "Other expenses" document with the "To cost price" switch, and it lands on products with a "Cost allocation" document. The expense is visible in the "Accumulated cost" report if its item belongs to the "Cost price" type.

Which base should you choose to allocate rent: amount or quantity?

For workshop rent, where the products are similar in the amount of work, "By quantity" fits, and every unit gets an equal share. "By amount" gives pricier products a larger share, which suits logistics costs.

What happens if a contractor's invoice arrives after the kitchen has been sold?

The cost in the sale is updated by reposting. Bimp runs a full repost automatically after midnight, and reposting the sales document gives an immediate result.